Ottawa Public Library Logo

Ottawa Public Library Board Meeting

Agenda 23

Tuesday, 31 January 2017

5:00 p.m.


Andrew S. Haydon Hall

Julie Tremblay, Library Board Assistant
613-580-2424 x32169

[email protected]

 

Board Members:

Chair:  Tim Tierney
Vice-Chair:  André Bergeron
Trustees:  Steven Begg, Allan Higdon, Kathy Fisher, Catherine McKenney, Scott Moffatt, Pamela Sweet,
Marianne Wilkinson

Accessible formats and communication supports, as well as simultaneous interpretation in both official languages, are available for any specific agenda item.  Please contact the OPL Board at [email protected] at least
two (2) business days in advance of the meeting to make a request.

REGRETS

 

DECLARATIONS OF CONFLICT OF INTEREST

 

CONFIRMATION OF MINUTES

 

Minutes 22 - Tuesday, 6 December 2016

 


 

CHAIR’S VERBAL UPDATE

 

CHIEF EXECUTIVE OFFICER'S REPORT

 

REPORTS

 

1.

CENTRAL LIBRARY DEVELOPMENT PROJECT: OTTAWA PUBLIC LIBRARY-LIBRARY AND ARCHIVES CANADA JOINT PROJECT

 

OPLB-2017-0101

 

1.    That the Ottawa Public Library Board receive the Ottawa Public Library (OPL)-Library and Archives Canada (LAC) Joint Project report including, the results of the Site Selection Process, and approve the closeout of Stage 1 of the Board-approved implementation process for the Central Library Development Project.
2.   That the Ottawa Public Library Board recommends that City Council approve the Ottawa Public Library-Library and Archives Canada (OPL-LAC) Joint Project for a new Ottawa Central Library as described in this report, and as follows:
a.   Approve proceeding with a partnership with Library and Archives Canada based on the overall assessment score, as detailed in the Ottawa Public Library Development Project OPL-LAC Partnership Assessment Report (Document 2);
b.   Approve the Central Library Development Project Relationship Framework, as outlined in this report and described in Document 3 with LAC for an OPL-LAC Joint Facility, subject to the approval of Government of Canada, and delegate the authority to negotiate and finalize a Relationship Agreement with Library and Archives Canada for the design, development, construction and operation of a joint facility to the CEO of the Ottawa Public Library, in consultation with the City Manager of the City of Ottawa and report back to OPL Board and City Council for approval of the detailed relationship agreement by June 2017, including as follows:
i.    That the Joint Facility be developed to be approximately 216,000 gross square feet (with an estimated 133,000 gross square feet allocated to OPL), that meets the intent of the functional building program requirements outlined in the Ottawa Public Library-Library and Archives Canada Joint Facility Master Program as described in this report and in Document 6;
ii.   That the City-owned site at 557 Wellington Street (Site 8) be the location of the new Ottawa Central Library, based on the approved site selection process described within this report and detailed in the Ottawa Central Library Development Project Site Evaluation Report (Document 8), and delegate the authority to the Director, Corporate Real Estate Office to take the necessary actions to assign the land for this project;
iii.  That the new Ottawa Central Library be delivered through a Design-Bid-Build procurement method as detailed in this report;
c.   Approve in principle the estimated City-funded portion, $99 million, of the total estimated project costs ($168 million, Class D estimates) and related funding  provisions as described in this report and set out in Document 12, and that the CEO of the OPL be directed to work with the City Manager to develop a funding strategy for the Ottawa Public Library/ City portion of the OPL-LAC Joint Facility and report back to the Board and City Council by June 2017, with the intention of seeking project authority to proceed to the Design stage, as described in this report;
d.   Direct the Director, Corporate Real Estate Office to investigate options to dispose of the existing assets at 120 Metcalfe Street/191 Laurier Avenue West and report back to the Ottawa Public Library Board, the Finance and Economic Development Committee, and City Council, as appropriate;
e.   Delegate the authority to the Director, Infrastructure Services to initiate the procurement process for the design process as described in this report, subject to the understanding that a contract will not be awarded until the Ottawa Public Library Board and City Council have approved the Relationship Agreement and the Funding Strategy;
f.    Direct City staff to undertake a detailed study into the parking requirements related to the OPL-LAC facility in order to clarify the expected need for public parking at the Joint Facility, confirming if any provision for parking aligns with the broader mandate of the City as well as that of the Municipal Parking Management Program, and report back to the Ottawa Public Library Board and City Council with a recommendation by March 2017.

 

*IN CAMERA ITEMS

 

NOTICES OF MOTION

 

OTHER BUSINESS

 

INQUIRIES

 

ADJOURNMENT

 

NEXT MEETING

Tuesday, 14 February 2017

 

Note:   1.         In Camera items are not subject to public discussion or audience.

2.         Any written or verbal submissions (including your name but excluding personal contact information) will form part of the public record and be made available to the Ottawa Public Library Board and the public.

No Item Selected